City Gas Gate Station Pressure Regulating Gas Supply

A simplified single-path city gate supplies gas through a trunk, regulator, and downstream branch to a terminal. Steady-state isothermal analysis checks outlet target, pressure-drop allocation, and flow at given boundary pressures.

Study Overview​

ItemConfiguration
ScenarioSingle-path city gate regulation
Network1 source, 2 pipes, 1 regulator, 1 load
AnalysisSteady-state, isothermal
BoundariesUpstream 0.4 MPag; downstream 0.02 MPag
ControlOutlet pressure 0.04 MPag
ResultsSupply, regulator pressures/drop, pipe losses, continuity
ScopePressure matching and steady-state supply capacity
Statussuccess / 100%

Working Conditions Background and Pipe Network Structure​

Working Condition Background​

Incoming pressure is 0.4 MPag, regulator target 0.04 MPag, and terminal 0.02 MPag. The downstream branch still needs pressure difference to overcome friction.

Pipe Network Structure​

City gas gate station pressure regulation model in NexusFlow gas pipeline network simulation platform
City gas gate station pressure regulation model in NexusFlow gas pipeline network simulation platform

City Gate Source → Urban Trunk → Regulator → Downstream Distribution Branch → Terminal.

The image labels Low-Pressure Branch and Residential Load identify the downstream branch and terminal.

One valve represents regulation; filtering, metering, heating, standby trains, shutdown, and venting are omitted. This suits normal-operation hydraulics and pressure control.

Pipeline and Equipment Parameters​

PipeLengthDiameterWallRoughnessFriction
Urban trunk2000 m300 mm8 mm0.045 mmColebrook
Distribution branch500 m150 mm5 mm0.045 mmColebrook

The entrance and exit elevations of the two sections of pipeline are both 0 m. This example does not consider the impact of terrain height difference on pressure distribution.

Boundary Conditions and Simulation Setup​

Air Source and Load Boundaries​

BoundaryLabelSetting
SourceCity Gate Source0.4 MPag pressure
LoadResidential Load0.02 MPag terminal pressure

Both ends impose pressure; boundaries, pipes, and regulation jointly determine steady flow.

Regulator Settings​

SettingValue
StateOpen
ModeOutlet pressure
Target0.04 MPag

The 20 kPa target-to-terminal difference is the downstream branch drop when regulation reaches target.

Simulation Settings​

SettingValue
Simulation / thermalSteady-state / isothermal
Temperature15 °C
EOSBWRS
GasNaturalGas
Gauge reference101.325 kPa(a)
Standard state101.325 kPa(a), 20 °C

NaturalGas mole percentages: methane 90%, ethane 5%, propane 2%, nitrogen 2%, carbon dioxide 1%.

Steady State Calculation Results and Analysis​

SectionInlet MPagOutlet MPagDrop kPaStandard Nm³/h
Trunk0.400000.399340.662277.17
Regulator0.399340.04000359.342277.17
Distribution branch0.040000.0200020.002277.17

Outlet reaches 0.04000 MPag. Drops total 380.00 kPa, matching boundaries; the regulator takes 94.6%.

Mass flow is equal across the regulator; standard flow is 2277.17 Nm³/h at both ends. Isothermal depressurization reduces density, increasing actual flow from 448.58 to 1603.04 m³/h.

Regulator setpoint, port pressures, and standard and actual flows
Regulator setpoint, port pressures, and standard and actual flows

The steady result instant is 2026-01-01 00:00:00. Data blocks use interface precision; use the table for drop.

Simulation Capabilities Reflected in Calculation Examples​

CapabilityApplication
Pressure-boundary solvingSupply flow from source/terminal pressures
RegulationDrop required for 0.04 MPag outlet
CouplingTrunk, valve, and branch pressures/flow
Loss allocationSeparate pipe and valve drops
ContinuitySeries standard flow and node conservation
Target checkActual versus set outlet pressure

Results Viewing Process​

  1. Open City Gate Pressure Regulation in Simulation Marketplace, start, and wait.
  2. Select the completed job; inspect steady residuals under Other Results.
  3. Create a regulator data block and check pressures, setpoint, and flows.
  4. Check both pipe pressures/drops and standard flow against the table.

The result viewing process only describes the result entry that needs to be checked in this case. For general job switching, trend chart and data block operation methods on the Workbench, see "Running calculations and viewing results" in the quick start.

Extended Comparison Conditions​

ComparisonChangeComparePurpose
TargetOutlet setpointValve/pipe drops and flowSupply effect
Lower supplySource pressureInlet, regulation, flowRegulation margin
Peak loadTerminal flow boundaryTerminal/minimum pressure, statePeak capacity
Branch modificationDiameter or lengthDrop, pressure, flowUpgrade comparison
Capacity limitEquipment capacity model/dataActive constraint, outlet, flowTarget reachability
Parallel regulationAdd parallel trainSplit, pressure, loadCoordination

When carrying out extended working condition comparison, only change a single parameter to be compared each time, and keep other boundary conditions and equipment parameters consistent. For load changes over time, switching of pressure regulating equipment or upstream pressure disturbances, transient operating conditions should be established based on this steady-state model, and corresponding time-varying boundaries or control conditions should be set.